ETV Bharat / state

36 railway projects under different stages of work in Odisha

At least 36 railway projects are going through different stages of preparation and consent in the state. After completion, it will cover a length of 4,567 km.

author img

By

Published : Dec 12, 2019, 11:43 AM IST

Representative Image
Representative Image

Bhubaneswar: At least 36 railway projects, falling fully or partly in Odisha, are under different stages of planning, approval or execution, the East Coast Railways said.

When completed, the projects costing Rs 49,984 crore will cover a length of 4,567 km.

Works including 10 new line projects covering a length of 1,269 km will be constructed at a cost of Rs 16,598 crore, of which 80 km length has been commissioned and an expenditure of Rs 4,260 crore incurred up to March 2019.

For a gauge conversion project covering a length of 140 km an estimated Rs 1,349 crore will be spent, of which 90 km length has been commissioned and an expenditure of Rs 191 crore incurred.

Similarly, 25 doubling projects covering a length of 3,159 km will be constructed at a cost of Rs 32,037 crore, of which 494 km length has been commissioned.

The timely completion of any railway project depends on various factors, such as quick land acquisition by the state government, forest clearance by officials of the forest the department, shifting of infringing utilities, statutory clearances from various authorities, geological and topographical conditions of the area.

For smooth execution of work, a lot of monitoring is done at various levels and regular meetings are held with the officials of the state government and authorities concerned to resolve the issues that are obstructing the progress of projects.

Also Read: Jaipur Metro alerted of a possible cyber attack

Bhubaneswar: At least 36 railway projects, falling fully or partly in Odisha, are under different stages of planning, approval or execution, the East Coast Railways said.

When completed, the projects costing Rs 49,984 crore will cover a length of 4,567 km.

Works including 10 new line projects covering a length of 1,269 km will be constructed at a cost of Rs 16,598 crore, of which 80 km length has been commissioned and an expenditure of Rs 4,260 crore incurred up to March 2019.

For a gauge conversion project covering a length of 140 km an estimated Rs 1,349 crore will be spent, of which 90 km length has been commissioned and an expenditure of Rs 191 crore incurred.

Similarly, 25 doubling projects covering a length of 3,159 km will be constructed at a cost of Rs 32,037 crore, of which 494 km length has been commissioned.

The timely completion of any railway project depends on various factors, such as quick land acquisition by the state government, forest clearance by officials of the forest the department, shifting of infringing utilities, statutory clearances from various authorities, geological and topographical conditions of the area.

For smooth execution of work, a lot of monitoring is done at various levels and regular meetings are held with the officials of the state government and authorities concerned to resolve the issues that are obstructing the progress of projects.

Also Read: Jaipur Metro alerted of a possible cyber attack

ZCZC
PRI ERG ESPL NAT
.BHUBANESWAR CES1
OD-RAIL-PROJECTS
36 railway projects under different stages of work in Odisha
         Bhubaneswar, Dec 12 (PTI) At least 36 railway
projects, falling fully or partly in Odisha, are under
different stages of planning, approval or execution, the East
Coast Railways said.
         When completed, the projects costing Rs 49,984 crore
will cover a length of 4,567 km.
Works including 10 new line projects covering a length
of 1,269 km will be constructed at a cost of Rs 16,598 crore,
of which 80 km length has been commissioned and an expenditure
of Rs 4,260 crore incurred up to March 2019, the ECoR said.
For a gauge conversion project covering a length of
140 km an estimated Rs 1,349 crore will be spent, of which 90
km length has been commissioned and an expenditure of Rs 191
crore incurred, the ECoR said.
         Similarly, 25 doubling projects covering a length of
3,159 km will be constructed at a cost of Rs 32,037 crore, of
which 494 km length has been commissioned.
         The timely completion of any railway project depends
on various factors, such as quick land acquisition by the
state government, forest clearance by officials of forest
department, shifting of infringing utilities, statutory
clearances from various authorities, geological and
topographical conditions of the area, the ECoR said.
         For smooth execution of work, a lot of monitoring is
done at various levels and regular meetings are held with the
officials of the state government and authorities concerned to
resolve the issues that are obstructing the progress of
projects, the ECoR said. PTI AAM
MM
MM
12120920
NNNN