LG Murmu asks for roof top solar systems for all govt buildings in J-K

author img

By

Published : Dec 4, 2019, 11:55 PM IST

In order to make the state more energy efficient, Lieutenant Governor of Jammu and Kashmir G C Murmu has issued a direction to provide 'roof top solar systems' to all government buildings. The directions were given by Murmu during the first meeting of Administrative Council yesterday.

s
s

Jammu: Lieutenant Governor G C Murmu has issued direction to provide 'roof top solar systems' to all government buildings in Jammu and Kashmir Union Territory as part of energy efficiency measures, a government spokesperson said.

The directions were given by Murmu during the first meeting of Administrative Council on Tuesday in which the power scenario across the union territory was reviewed, the official spokesperson said.

Power Development Department Commissioner-Secretary Hirdesh Kumar made a detailed presentation highlighting the power scenario in Jammu and Kashmir, including the status of restoration of power supply post snowfall on November 6 and 7 in Kashmir region.

Murmu directed to conduct audit of all 220 KV and 132 KV transmission line towers and take corrective measures before the start of the next winter season to prevent damage to power structure, he said.

The Administrative Council was apprised that after commissioning of 220 KV Zainakote-Aulesteng line, which is expected by the end of February 2020, an additional 320 MVA capacity will be added to the system which will bring much needed relief in Kashmir region and bring down power curtailment.

The Council was also apprised that the Power Development Department has fixed target of achieving 100 per cent metering by installing prepaid and smart meters by March 2021.

Following snowfall, the power supply in the entire Kashmir region was severely affected, especially in districts of Bandipora, Baramulla, Kupwara and Shopian, the Council was informed.

The districts of Anantnag, Kulgam, Pulwama and Budgam were also badly affected.

The entire load in the Kashmir region on the evening of November 7 plummeted to 30 MW, he said.

Restoration works were initiated on a war footing and power supply was fully restored in districts of Srinagar, Ganderbal, Pulwama, Shopian, Anantnag and Kulgam by November 10, the spokesman said.

However, due to the collapse of transmission line towers of the lines feeding Nihalpul, Amargarh and Magam grids, the power supply to districts of Budgam, Baramulla, Kupwara and Bandipora was restored by erecting Emergency Restoration Structures (ERS), he added.

Also Read: Father of road accident victim distributes helmets at condolence meet in MP

Jammu: Lieutenant Governor G C Murmu has issued direction to provide 'roof top solar systems' to all government buildings in Jammu and Kashmir Union Territory as part of energy efficiency measures, a government spokesperson said.

The directions were given by Murmu during the first meeting of Administrative Council on Tuesday in which the power scenario across the union territory was reviewed, the official spokesperson said.

Power Development Department Commissioner-Secretary Hirdesh Kumar made a detailed presentation highlighting the power scenario in Jammu and Kashmir, including the status of restoration of power supply post snowfall on November 6 and 7 in Kashmir region.

Murmu directed to conduct audit of all 220 KV and 132 KV transmission line towers and take corrective measures before the start of the next winter season to prevent damage to power structure, he said.

The Administrative Council was apprised that after commissioning of 220 KV Zainakote-Aulesteng line, which is expected by the end of February 2020, an additional 320 MVA capacity will be added to the system which will bring much needed relief in Kashmir region and bring down power curtailment.

The Council was also apprised that the Power Development Department has fixed target of achieving 100 per cent metering by installing prepaid and smart meters by March 2021.

Following snowfall, the power supply in the entire Kashmir region was severely affected, especially in districts of Bandipora, Baramulla, Kupwara and Shopian, the Council was informed.

The districts of Anantnag, Kulgam, Pulwama and Budgam were also badly affected.

The entire load in the Kashmir region on the evening of November 7 plummeted to 30 MW, he said.

Restoration works were initiated on a war footing and power supply was fully restored in districts of Srinagar, Ganderbal, Pulwama, Shopian, Anantnag and Kulgam by November 10, the spokesman said.

However, due to the collapse of transmission line towers of the lines feeding Nihalpul, Amargarh and Magam grids, the power supply to districts of Budgam, Baramulla, Kupwara and Bandipora was restored by erecting Emergency Restoration Structures (ERS), he added.

Also Read: Father of road accident victim distributes helmets at condolence meet in MP

ZCZC
PRI ECO NRG
.JAMMU NRG13
JK-LG-SOLAR
LG Murmu asks for roof top solar systems for all govt buildings in J-K
          Jammu, Dec 4 (PTI) Lieutenant Governor G C Murmu has issued direction to provide 'roof top solar systems' to all government buildings in Jammu and Kashmir Union Territory as part of energy efficiency measures, a government spokesperson said.
          The directions were given by Murmu during the first meeting of Administrative Council on Tuesday in which the power scenario across the union territory was reviewed, the official spokesperson said
          Power Development Department Commissioner-Secretary Hirdesh Kumar made a detailed presentation highlighting the power scenario in Jammu and Kashmir, including the status of restoration of power supply post snowfall on November 6 and 7 in Kashmir region.
          Murmu directed to conduct audit of all 220 KV and 132 KV transmission line towers and take corrective measures before the start of the next winter season to prevent damage to power structure, he said.
          The Administrative Council was apprised that after commissioning of 220 KV Zainakote-Aulesteng line, which is expected by the end of February 2020, an additional 320 MVA capacity will be added to the system which will bring much needed relief in Kashmir region and bring down power curtailment.
          The Council was also apprised that the Power Development Department has fixed target of achieving 100 per cent metering by installing prepaid and smart meters by March 2021.
          Following snowfall, the power supply in the entire Kashmir region was severely affected, especially in districts of Bandipora, Baramulla, Kupwara and Shopian, the Council was informed.
          The districts of Anantnag, Kulgam, Pulwama and Budgam were also badly affected.
          The entire load in the Kashmir region on the evening of November 7 plummeted to 30 MW, he said.
          Restoration works were initiated on a war footing and power supply was fully restored in districts of Srinagar, Ganderbal, Pulwama, Shopian, Anantnag and Kulgam by November 10, the spokesman said.
          However, due to the collapse of transmission line towers of the lines feeding Nihalpul, Amargarh and Magam grids, the power supply to districts of Budgam, Baramulla, Kupwara and Bandipora was restored by erecting Emergency Restoration Structures (ERS), he added. PTI AB
RVK
12041708
NNNN