Mumbai: Town planning authority MMRDA on Friday said the second phase of the much-delayed Jacob Circle-Wadala-Chembur monorail project is likely to commence operations from March 1.

Mumbai monorail
author img

By

Published : Feb 8, 2019, 10:15 PM IST

The Mumbai Metropolitan Region Development Authority (MMRDA), which is implementing the 19.5 km long corridor, has received spare parts required to repair the rakes that were gutted in a fire accident in 2017.

"The much awaited monorail parts worth over Rs 3 crore have arrived in the city from Malaysia which will now help MMRDA begin the phase-2 of the project. We are hopeful to commence operations on the Jacob Circle-Wadala corridor from March 1 this year," MMRDA Joint Project Director Dilip Kawathkar said in a statement issued here.

He said the parts will enable MMRDA refurbish four more mono trains into the service of Mumbaikars.

"This means the entire monorail corridor will operate with seven trains. Once commissioned, the entire route will attract many more commuters," Kawathkar added.

The MMRDA has also decided to increase the fares to Rs 10 to Rs 40 for the entire corridor from the current Rs 5 to Rs 11 for the first phase.

MMRDA took over the operations and maintenance of the monorail from Scomi Engineering in the month of December 2018, after it failed to supply the contracted rakes and other operational materials, including the signalling equipment and maintaining the quality of monorail services despite many extensions.

On December 14, town planning authority MMRDA had terminated its contract with the LTSE consortium, which had the contract to build the country's first and only monorail in the megapolis.

Last year one rake went up in flames, while on service, and it forced shutting of the services for many months.

The L&T-Scomi consortium won the Rs 2,460-crore contract in 2009 to build and operate the 19.5-km monorail network on the Chembur-Wadala-Jacob Circle corridor connecting the eastern periphery of the island city to the central parts.

The 8.9-km-long first phase of the monorail from Chembur to Wadala was opened to the public in February 2014, almost four years after the original deadline.

undefined

The Mumbai Metropolitan Region Development Authority (MMRDA), which is implementing the 19.5 km long corridor, has received spare parts required to repair the rakes that were gutted in a fire accident in 2017.

"The much awaited monorail parts worth over Rs 3 crore have arrived in the city from Malaysia which will now help MMRDA begin the phase-2 of the project. We are hopeful to commence operations on the Jacob Circle-Wadala corridor from March 1 this year," MMRDA Joint Project Director Dilip Kawathkar said in a statement issued here.

He said the parts will enable MMRDA refurbish four more mono trains into the service of Mumbaikars.

"This means the entire monorail corridor will operate with seven trains. Once commissioned, the entire route will attract many more commuters," Kawathkar added.

The MMRDA has also decided to increase the fares to Rs 10 to Rs 40 for the entire corridor from the current Rs 5 to Rs 11 for the first phase.

MMRDA took over the operations and maintenance of the monorail from Scomi Engineering in the month of December 2018, after it failed to supply the contracted rakes and other operational materials, including the signalling equipment and maintaining the quality of monorail services despite many extensions.

On December 14, town planning authority MMRDA had terminated its contract with the LTSE consortium, which had the contract to build the country's first and only monorail in the megapolis.

Last year one rake went up in flames, while on service, and it forced shutting of the services for many months.

The L&T-Scomi consortium won the Rs 2,460-crore contract in 2009 to build and operate the 19.5-km monorail network on the Chembur-Wadala-Jacob Circle corridor connecting the eastern periphery of the island city to the central parts.

The 8.9-km-long first phase of the monorail from Chembur to Wadala was opened to the public in February 2014, almost four years after the original deadline.

undefined

Also read: Mumbai University discovers technology to preserve food for 3 yrs

With inputs from PTI.

ZCZC
URG ESPL NAT WRG
.MUMBAI BES17
MH-MONORAIL
Jacob Circle-Wadala monorail project likely to commence
operations from March 1
         Mumbai, Feb 8 (PTI) Town planning authority MMRDA
Friday said the second phase of the much-delayed Jacob
Circle-Wadala-Chembur monorail project is likely to commence
operations from March 1.
         The Mumbai Metropolitan Region Development Authority
(MMRDA), which is implementing the 19.5 km long corridor, has
received spare parts required to repair the rakes that were
gutted in a fire accident in 2017.
         "The much awaited monorail parts worth over Rs 3 crore
have arrived in the city from Malaysia which will now help
MMRDA begin the phase-2 of the project. We are hopeful to
commence operations on the Jacob Circle-Wadala corridor from
March 1 this year," MMRDA Joint Project Director Dilip
Kawathkar said in a statement issued here.
         He said the parts will enable MMRDA refurbish four
more mono trains into the service of Mumbaikars.
         "This means the entire monorail corridor will operate
with seven trains. Once commissioned, the entire route will
attract many more commuters," Kawathkar added.
         The MMRDA has also decided to increase the fares to Rs
10 to Rs 40 for the entire corridor from the current Rs 5 to
Rs 11 for the first phase.
         MMRDA took over the operations and maintenance of the
monorail from Scomi Engineering in the month of December 2018,
after it failed to supply the contracted rakes and other
operational materials, including the signalling equipment and
maintaining the quality of monorail services despite many
extensions.
         On December 14, town planning authority MMRDA had
terminated its contract with the LTSE consortium, which had
the contract to build the country's first and only monorail in
the megapolis.
         Last year one rake went up in flames, while on
service, and it forced shutting of the services for many
months.
         The L&T-Scomi consortium won the Rs 2,460-crore
contract in 2009 to build and operate the 19.5-km monorail
network on the Chembur-Wadala-Jacob Circle corridor connecting
the eastern periphery of the island city to the central parts.
         The 8.9-km-long first phase of the monorail from
Chembur to Wadala was opened to the public in February 2014,
almost four years after the original deadline. PTI PSK