New Delhi: Over 50 projects of the Central government that are being implemented in the state of Andhra Pradesh are facing severe cost and time overrun, with a delay of nearly two decades in one case while the total cost overrun amounts to more than Rs 54,000 crore, showed the latest official data.
According to the data shared by the government in the Rajya Sabha, there are 56 ongoing central projects in Andhra Pradesh that have a project cost of over Rs 150 crore and are being monitored by the ministry of statistics and programme implementation.
These projects are related railways, highways, petroleum refining sector and water irrigation projects, among other things. As per a flash report generated by the ministry’s Online Computerized Monitoring System (OCMS) of the Ministry in February this year, there are 56 central projects in Andhra Pradesh with the original cost of over Rs 1.01 lakh crore.
The data showed that the anticipated cost of these projects is now above over Rs 1.54 lakh crore, an increase of more than 52 percent. Out of these 56 projects having the original cost of over Rs 150 crores, more than 40 percent or total 24 projects have time overruns.
Kotlpalli-Naraspur Railway project delayed by 18 years-According to the data, the KOTLPALLI-NARASAPUR project of the South Central Railway, which was approved in December 2001 at the original cost of Rs 1045.2 crore with the completion scheduled in March 2009, has been delayed by 18 years and is expected to be completed in March 2027 with a cost of over Rs 2,500 crores.