Amaravati: In a major setback to the Y S Jaganmohan Reddy government, the Andhra Pradesh High Court on Thursday stayed the operation of an order constituting a high-level negotiation committee for renegotiating the power purchase agreements with wind and solar developers.
Justice M Ganga Rao stayed the order issued on July 1 for four weeks on a batch of petitions filed by about 40 wind and solar power generating companies.
The judge directed the state government to file its counter and posted the case to August 22 for further hearing.
It may be recalled that the Jaganmohan Reddy government took a decision to review all the power purchase agreements (PPA) signed by the previous Chandrababu Naidu regime with wind and solar power generators and constituted a high-level committee to renegotiate the prices.
The Centre wrote at least two letters to the state government, asking it not to go ahead with such review as it would adversely affect investments into the power sector.
Read More:PMO asks Finance Ministry to have re-look at sovereign bond proposal
Ignoring the Centre's advice, the Reddy government was going ahead with the review exercise, saying the PPAs caused a loss of about Rs 5,000 crore to the state exchequer.
In this backdrop, the private power producers moved the high court seeking scrapping of GO 63.
He also challenged the letters sent by the AP Southern Power Distribution Company Limited, threatening to cancel the PPAs if the prices were not cut.
Presenting the arguments on behalf of the petitioners, senior advocate Mukul Rohatgi pointed out that the power producers bagged the contracts based on competitive bidding.