New Delhi:The Supreme Court on Monday said the demolition work for the two 40 story towers constructed by Supertech in Noida, will begin in two weeks.
A bench headed by Justice D.Y. Chandrachud directed the Noida CEO to commence the demolition work within two weeks, and also convene a meeting with all agencies concerned, including GAIL, within 72 hours to finalise the schedule and the dates for the demolition.
The top court was informed that GAIL's NOC was required as there is a high pressure underground natural gas pipeline, which is passing at a distance of 15 metres and depth of 3 mets.re The court was also informed that the Defence Ministry will provide the explosives for the demolition.
In its August 31 judgment, the Supreme Court, besides ordering demolition of Supertech twin towers in Noida and refund for the flat purchasers, ordered prosecution of errant NOIDA and real estate company officials under Section 49 of Uttar Pradesh Urban Development (UPUD) Act for their "nefarious complicity", which resulted in the construction of towers.