Mumbai: In a significant development, the Mumbai Metro Rail Corporation Limited (MMRCL) successfully conducted the trial run of Metro-3 subway route. The 42nd and final phase of the subway project was completed at Mumbai Central station on MMRCL's Colaba-Bandra-Seepz Metro-3 route. The tunnelling on the upline route took a total of 43 days.
One of the longest stretches of the Metro-3 route, the package-3 includes metro stations Mumbai Central, Mahalakshmi, Science Museum, Acharya Atre Chowk and Worli. Robbins' TBM Tansa-1 successfully completed the most challenging tunnelling work of 837 meters from Mahalakshmi Metro Station to Mumbai Central Metro Station under package-3. This test was conducted from metro rail line three, where the subway work was undertaken.