New Delhi: Land acquisition, delay in supply of equipment, and changes in regulations are some of the critical issues that have hampered the commissioning of as many as 17 mega thermal power projects in India. The projects having a total capacity of 17,000 MW are spread across eight states. Such delay already resulted in both time and cost overruns.
According to the government statistics available with ETV Bharat, four projects in Bihar, two projects in Jharkhand, one 800 MW thermal power project in Madhya Pradesh, two projects in Odisha, two projects in Rajasthan, one 500 MW project in Tamil Nadu, one 1600 MW thermal power project in Telangana and four delayed projects with a power generating capacity of 4620 MW in Uttar Pradesh have posed a big challenge for India's power generating capacity. Four projects in Bihar with a power generating capacity of 4210 MW have already registered both costs and time overruns.
According to the government statistics, three units of Barh STPP-I, NTPC, and others have already registered a cost overrun of 145.16 percent from their original costs of Rs 8693 crore. It has also registered a time overrun of 134 to 136 months. Similarly, two power projects in Jharkhand with a capacity of 2780 MW also registered a cost overrun of 5.55 percent and a time overrun of 44 months.
"There are various factors and issues which affect the execution and completion of power projects. The issues also vary from sector to sector," a senior official in the power ministry told this correspondent. As per the government records, the Covid-19 pandemic has also affected the execution of the projects.
Issues in land acquisition (procedural delays, unavailability of land records, court cases, unreasonable demands by landowners, and changes in the land acquisition act) are some of the factors that hamper the commissioning of the thermal power projects.