Panaji:More than 50,000 trees have been cut for the upcoming Mopa greenfield airport whose first phase is expected to be completed by 2022, Chief Minister Pramod Sawant said on Wednesday.
He told the Assembly in a written reply tabled on Wednesday that nearly 20 per cent of the work had been completed till date. The airport is located on the Mopa plateau in North Goa.
"Mopa airport's construction is in progress. The first phase is expected to be commissioned in 2022. The physical progress up to December 12, 2020, is 19.59 per cent," Sawant said.
Read:SC lifts suspension on environmental clearance granted for Mopa airport