Nasik: It has been a tough phase for the ambitious Samruddhi Expressway project for the past three months. The pace of 750-km first linear project of the country has slowed down after workers of the project have returned home.
The pace of the Samruddhi Expressway, also called as 'Nagpur-Mumbai Super Communication', which passes through 10 districts of the state, has slowed down as most of the workers have returned home citing corona scare. The state government even gave permission for the construction work of the project amid lockdown but still the project has failed to gain momentum.
According to reports, the construction work of Samruddhi Expressway is partially stuck as more than half of the workers engaged in the project have returned homes. Seeing the delay, the concerned authorities have decided to extend the deadline of the project.
Anil Kumar Gaikwad, Joint Director, MSRDC, said, "More than 50 per cent of our employees have returned home. We are not able to start work in a full-fledged manner. The responsibility lies with the contractor to arrange the workers."