Gurdaspur (Punjab): The Ministry of Home Affairs Additional Secretary Govind Mohan who visited the site of the Kartarpur corridor on Wednesday said that the work will be completed on time, i.e. October 31.
"The work has been completed for about 75 percent so far. The work is underway and is at a good speed. The whole building will be completed and handed over to the government by 31st October. We also have communication on both sides and the work is in progress," Mohan added.
He further said that currently there is a parking facility for around 200 cars but it is being expanded for at least 1000 cars.
The authorities are also getting golf carts to facilitate senior citizens and physically handicapped people.
"I am very happy that the corridor is going to be completed soon. I have been wanting to visit the gurudwara for a long time," said Kulwant Kaur, a resident of the area.