New Delhi: With the completion of the underground tunnel for the Golden Line metro stations between Chhatarpur Mandir and IGNOU on Tuesday, the Delhi Metro Rail Corporation (DMRC) has achieved yet another feat in Phase IV metro extension work.
This one of the deepest tunnels was bored with a 97-meter-long tunnel-boring machine (TBM). The tunnel was constructed using the EPBM (Earth Pressure Balancing Method) technology, in which concrete lining of precast tunnel rings was done. These rings were prepared in the automated casting yard set up in Mundka. Quick strength was provided through a steam curing system.
The tunnelling started in 2023 but faced several hurdles like steep slopes and hard rocks which damaged the screw auger of the TBM. DMRC followed all necessary safety measures during tunnel boring with installations of high-sensitivity equipment under the existing viaduct and surrounding structures to avert any possibility of land collapse.